could you please correcth this for me ( i am in urgent need for it):

Steps of tendering process

1. Preparing Designs and Tenders documents:

- The Engineering and consulting firm prepare the designs with co-operation with the beneficiary

- CRS staff (program manager, project officer, and engineer) discusses the designs and making any necessary changes.

- Getting the final approval from the beneficiary.

- Then the engineering firm prepare bill of quantity taking in consideration the budget.

- Review bill of quantity from CRS staff and making any necessary changes.

- Photocopy 15 copy from the tender or less.

2. Advertising & selling tenders:

- Announce tender advertisement in tow local newspaper for one day or one local newspaper for two days.

- Send a copy of the advertisement to Contractor Union & engineering syndicate.

- Sending an invitation letters to 10 or more contractors in project area, in case of closure or any reason which prevent newspaper to reach.

- Arranging a visit to the project site from the contractors after three days from starting of selling tender, and in this day we stop selling tender for any contractor.

- After field visit a meeting arranged between CRS staff, consultant office, contractors to answer any questions related to the quantities, designs, etc…….

3. Opening tenders & taking the decision:

- Opening tender session included representatives from ministry of local government, Ministry of interior, municipality, beneficiary, engineering consultant firm, and contractors.

- Tenders which received after close time is never accepted.

- After opening tenders the engineers revise the tenders to be sure that all calculations are right and all proper documents are available.

- Making an overall evaluation for tenders from the engineers (contractors name, prices, degrees, documents……………)

- Asking about first three contractors reputation from three trusted sources or more (municipality, donor, etc) which contractor has implemented projects for them in last two years.

- Taking the primary decision and sending it to B.Hanina office with all documents.

- After B. Hanina office approval, we arrange a meeting of our committee which consists of representatives of interior ministry, local government ministry, municipality, engineering consultant firm, beneficiary to get the final approval for the decision.

- Sending an acceptance letter for chosen contractor and apology letters for other contractors.

- Asking the contractor to prepare his guarantees (performance & delay guarantees) during one week

- Signing the contract.
  

Top answer

OK, Main comment. When you do a list, the grammatical form of each item in the same list must be the same. So if you start the first two items with a verb then all other must start with a verb.

  • OK, Main comment.
  • When you do a list, the grammatical form of each item in the same list must be the same.
  • So if you start the first two items with a verb then all other must start with a verb.
  • And be consisten on your punctuation.
  • Do not end one with a period and not another.
Free · every Monday

Get the Weekly English Kit 📬

New words, one handy idiom, and a 2-minute quiz — delivered to your inbox to keep your streak alive.

1 Answers
0
OK, Main comment. When you do a list, the grammatical form of each item in the same list must be the same. So if you start the first two items with a verb then all other must start with a verb. And be consisten on your punctuation. Do not end one with a period and not another.

Engineering and consulting firm prepares the designs with co-operation of the beneficiary