1. We will not perform the inspection if there is no 100% goods ready and the inspection will move to 27 March instead of 26 March now. Please ensure you can catch the vessel closing on 28 March 12:00.
2. You are break the commitment to slip the schedule for again. We have advised to the customer that 300 pcs will be air shipped on March 26 and balance quantity will catch with vessel ETD March 29. Please keep an eye for it and not further delay will be accept, we cannot help if the customer request to air the whole quantities 1,600 pcs finally at your company cost, as this is the manufacture fault.