Sharmanshariff Posted 7 years ago
Letter Writing

Comments on my letter please

Reference to the above, your letter xxx/xxx/xxx dated 17th December 2018 and to previous weekly meetings held between xxx and yyy, the method of pit construction for Q01-58 was changed from cast in-situ to sheet piles due to reasons stated below:

  1. The possibility of hitting existing utilities is high if we are to use the cast in-situ method (refer drawing attached, attachment A)
  2. From the soil investigation data gathered, the area is of hard ground which is almost impossible to drive sheet piles using conventional means (refer borehole record, attachment B)
  3. This necessitates the usage of a prebore machine; which has a cost impact; which in our opinion, should be borne by you.

Apart from the above, sheet piles have to be cut in order to retrieve the cutter heads upon completion of our jacking works. Thus, we have to disagree on your statement as per your letter above where we would be held responsible for all cost and expenses if the sheet piles are damaged or stolen/missing.


Moving forward, we would like to request a meeting with your contract department to discuss and finalize on this matter.


Your cooperation on this matter is much appreciated.

  

Top answer

I am not familiar with your project or construction methods. I can only comment on the grammar. ) This recommendation and summary is a follow up to your letter ***/***/*** dated 17 th December 2018 and to previous weekly meetings held between 11/03/2018 and 12/16/2018.

  • I am not familiar with your project or construction methods.
  • I can only comment on the grammar.
  • ) This recommendation and summary is a follow up to your letter ***/***/*** dated 17 th December 2018 and to previous weekly meetings held between 11/03/2018 and 12/16/2018.
  • The method of pit construction for Q01-58 was changed from cast in-situ to sheet piles due to the following reasons stated below : The possibility of hitting existing utilities is high if we are to use the cast in-situ method (refer drawing attached, attachment A) From the soil investigation data gathered, the area is of hard ground which is almost impossible to drive sheet piles using conventional means (refer borehole record, attachment B) This necessitates the usage of a prebore machine , which has a cost impact .
  • And this increase which in our opinion, should be borne by you.
Free · every Monday

Get the Weekly English Kit 📬

New words, one handy idiom, and a 2-minute quiz — delivered to your inbox to keep your streak alive.

1 Answers
0

I am not familiar with your project or construction methods. I can only comment on the grammar.


Reference to the above, (What is above?)

This recommendation and summary is a follow up to your letter ***/***/*** dated 17th December 2018 and to previous weekly